Property | Data type | Value | Description | Condition | Mode |
Not defined | Integer | 0 | Appointment is not typed-link to another one | Only CHAINCONSTRAINTORDER, CHAINCONSTRAINTMINDELAY OR CHAINCONSTRAINTMAXDELAY defined on the chain model are used and values on each appointment are used | |
Spacing (and ordering) | Integer | 1 | Appointments linked are time-spaced (unit=days / 0=same days / 1=day and day after / 2=one day interleaved...)Number of day is defined by CHAINCONSTRAINTMINDELAY or CHAINCONSTRAINTMAXDELAY (NOT BOTH), Ordering may be defined with CHAINCONSTRAINTORDER | Constraints have to be compatible each others | |
Same resource | Integer | 2 | Appointments linked have to be planned to same resource | Resources have to be able to do these appointments (resources priorities/skills/jobs/worked-days/distances...). Obviously inconsistent if combined with "Same Start" |
|
Grouped : The maximum spacing relates to the first appointment | Integer | 8 | Appointments linked cannot be spaced more than N days from the first appointment of the chainNumber of day is defined by CHAINCONSTRAINTMAXDELAY | The maximum space between days is defined in DAY unitAppointments planned are into the time scope of the scheduling process usedSome appointments may not to be planned | |
Grouped + Same resource | Integer | 10 | Combine constraint Same Resource (2) with constraint "grouped" (8, maximum spacing relates to first)Value 10=8+2 | The resource have to be able to do these appointments (resource priority/skill/job/worked-days/distance...) | |
Delayed : The minimum spacing relates to the first appointment | Integer | 16 | Appointments linked cannot be spaced less than N days from the first appointment of the chainNumber of day is defined by CHAINCONSTRAINTMINDELAY | The minimum space between days is defined in DAY unitAppointments planned are into the time scope of the scheduling process usedSome appointments may not to be planned | |
Delayed + Same resource | Integer | 18 | Combine constraint Same Resource (2) with constraint "Delayed" (18, minimum spacing relates to first)Value 10=8+2 | The resource have to be able to do these appointments (resource priority/skill/job/worked-days/distance...) | |
Same start | Integer | 32 | Appointments linked must start the same day at same time (even if they have distinct duration and requirements) | Obviously inconsistent if combined with "Same Resource" | |
Distinct days | Integer | 256 | Appointments linked cannot be planned the same day | The minimum space between days is defined to 1Some appointments may not to be planned | |
Ordered Tour | Integer | 514 | Appointments linked have to be done the same day, by the same resourceValue 514=; CHAINCONSTRAINTORDER field have to be defined and managed | Some appointments may not to be planned if there is not enough time into the worked day | |
Ordered Circuit | Integer | 518 | Appointments linked have to be done the same day, by the same resource, one by one without any other appointment inserted into the chainValue 518=; CHAINCONSTRAINTORDER field have to be defined and managed | Some appointments may not to be planned if there is not enough time into the worked day | Dispatcher formulae doesn't works every time |
Circuit | Integer | 14 | Appointments linked have to be done by the same resource, one by one without any other appointment inserted into the chainValue 14=2+4+8 with Space between appointments forced to 0 days; CHAINCONSTRAINTORDER field is managed | Some appointments may not to be planned if there is not enough time into the worked day | ONLY with RealTime Optimization Engine |
Stappling | Integer | 1030 | Appointments linked have to be done on many days, by the same resource, one by one without any other appointment inserted into the chainCHAINCONSTRAINTORDER is managedAll or none appointment are planned | Appoinments have same location, same resource, no orderingThe system considers appointments as ONE long appointment, plan it virtualy and then put each link subsequently without any other constraintAll or none appointments of each chain are planned | ONLY with RealTime Optimization Engine |